Through this service, you can request to modify a water desalination self-supply licence.
Service Condition:
- Pass the technical, financial,and legal evaluation stage to obtain the eligibility for the service
- Pass the 28 days public notice without external objection
Required documents:
- Details of parent companies and affiliates with DoE water production licenses, including ownership interests and capacities
- Location of RO plant with schematic drawing and description
- Organizational chart of RO plant team
- Reference list of contractor experience
- Company contingency plan for RO and power system failure
- Details of chemicals used in RO operation
- Audited financial statements
- Constitutional documents of proposed licensee
- Details of construction contractors and operators, demonstrating capabilities
- Certificate of Completion of Building
- Certificates of Conformity (CoC)
Service Steps:
- Registration (Log in)
- Submit the application through the available channels and upload required documents
- Select the license type
- Pay applicable fees if application is approved
- Receive the license electronically
Service Beneficial: Government and Business
Service Fees: 50000 AED
Time duration for service completion: 30 working days from full Submission date