Through this service, you can obtain a new self-supply licence that allows you to treat wastewater where the production capacity is more than 100 m3/day.

Service Condition:

  1. Pass the technical, financial, and legal evaluation stage to obtain the eligibility for the service
  2. Pass the 28 days public notice without external objection

Required documents:

  1. Engineering drawing of the collection, treatment, and disposal system, including trade effluent discharges
  2. Recycled Water Safety Plan (RWSP)
  3. Schematic flow diagram of wastewater system at the site
  4. Compliance sheet with Abu Dhabi Uniform Plumbing Code 2009
  5. Schematic flow diagram of collection, treatment, and disposal systems at the site (see Annex 1 for example)
  6. Process & Instrumentation Drawings (PID)
  7. Recycled Water & Biosolids Safety Plan
  8. Reference list of contractor experience in design, installation, and operation
  9. Detailed operational organizational chart for wastewater systems
  10. List of procedures for operation and maintenance of wastewater system
  11. Audited financial statements of Applicant
  12. Certificate of Completion of Building
  13. Certificates of Conformity (CoC)

Service Steps:

  1. Registration (Log in)
  2. Submit the application through the available channels and upload required documents
  3. Select the license type
  4. Receive approval or rejection of application
  5. Pay applicable fees if application is approved
  6. Receive the license electronically

Service Beneficial: Government and Business

Service Fees: 50000 AED + Evaluation fee: depending on individual circumstances

Time duration for service completion: 30 working days from full Submission date

 