Through this service, you can request to modify an electricity generation self-supply licence.

Service Condition:

  1. Pass the technical, financial,and legal evaluation stage to obtain the eligibility for the service
  2. Pass the 28 days public notice without external objection

Required documents:

  1. Summary table showing power station projects
  2. Power Generation Station Project roadmap
  3. Generation Electrical Transmission Code and Electrical Distribution Code compliance statement/report
  4. Connection Agreement with Transmission/Distribution System operator
  5. Technical data, specifications, capacities, and performance criteria
  6. Single Line Diagram (SLD) of the premises
  7. Electricity Operator/Maintenance Company profile
  8. Copies of audited accounts for parent companies
  9. Constitutional documents of the proposed licensee
  10. Details of proposed construction contractor(s) and operator(s)
  11. Details of parent companies and affiliates
  12. Certificate of Completion of Building
  13. Certificates of Conformity (CoC)

Service Steps:

  1. Registration (Log in)
  2. Submit the application through the available channels and upload required documents
  3. Select the license type
  4. Pay applicable fees if application is approved
  5. Receive the license electronically

 

Service Beneficial: Government and Business

Service Fees: 50000 AED

Time duration for service completion: 30 working days from full Submission date

 

X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm