Through this service, you can request to modify an electricity generation development licence.
Service Condition:
- Pass the technical, financial,and legal evaluation stage to obtain the eligibility for the service
- Pass the 28 days public notice without external objection
Required documents:
- Audited financial statements
- Constitutional documents of proposed licensee
- Details of construction contractor(s) and operator(s)
- Details of licensee's parent companies and affiliates
- Project Operating & Maintenance (O&M) costs
- Summary table of power station projects
- Power Generation Station Project roadmap
- Generation ETC and EDC compliance statement/report
- Copy of connection Agreement
- Technical data, specifications, and performance criteria
- Single Line Diagram (SLD) of premises
- Operator/Maintenance Company profile
- Certificate of Completion of Building
- Certificates of Conformity (CoC)
Service Steps:
- Registration (Log in)
- Submit the application through the available channels and upload required documents
- Select the license type
- Pay applicable fees if application is approved
- Receive the license electronically
Service Beneficial: Government and Business
Service Fees: 50000 AED
Time duration for service completion: 30 working days from full Submission date